The project involves detailed cost estimation and duration analysis of a building constructed by MIVAN formwork and Conventional formwork. The buildings are of G+21 floors where the saleable area of building with Mivan formwork is 8747.28 S.ft and that with Conventional Method is 9786.67 Sft on each floor with 3.0 m as the height of each floor. Later comparative analysis is done on cost and duration of both the buildings.
Keywords
MIVAN Formwork, Conventional Formwork, Detailed Estimation, Duration, Comparison.