Challenges of Financing Infrastructure Deficits Through PPPs : Lessons from Global Experience
Subscribe/Renew Journal
Public – private partnerships (PPPs) are increasingly being used globally to bridge infrastructure gaps. PPPs leverage private finances with public funds, thereby meeting infrastructure requirements of countries. PPPs also provide advantages of improved service quality and proper risk management. However, literature posits that PPPs are characterized by the presence of an array of challenges, making such projects vulnerable to distresses and/or cancellations. For instance, during the period from 2005–2018, 76 projects were declared cancelled/distressed, out of which 17 projects were in India alone, that too in a single year, that is, 2012. Against this backdrop, the objective of the present study was to identify the critical challenges pertaining to the lifecycle of PPP projects to enable policymakers formulate policies which minimize the risk of distress in PPP projects. The research methodology adopted was to rely on multiple case studies of PPP projects that had experienced challenges across the three phases of their project life cycle. Phase-1 of the cycle, known as the project development phase, was prone to challenges such as insufficient bids, inadequate competition, and poor feasibility analysis. Select challenges arising in Phase-2, the construction phase, were land acquisition, delays, and cost overruns. Finally, in Phase-3, which corresponded to the operational phase, challenges such as market demand risk and lower than expected revenues existed. Primarily relying on PPP projects in the transport sector, case studies were selected from countries such as India, Ghana, and Australia. Based on the enriching analysis from 12 such case studies, the paper concluded by providing a broad policy perspective.
Keywords
Infrastructure, Infrastructure Deficits, Public – Private Partnerships (PPPs), Case Study, India.
JEL Classification : H54, E60, O18, O22.
Paper Submission Date : February 10, 2020; Paper Sent Back for Revision : June 15, 2020; Paper Acceptance Date : June 28, 2020.
User
Subscription
Login to verify subscription
Font Size
Information
- Ameyaw, E. E., & Chan, A. P. (2013). Identifying public-private partnership (PPP) risks in managing water supply projects in Ghana. Journal of Facilities Management, 11(2), 152-182. http://dx.doi.org/10.1108/14725961311314651
- Asian Development Bank. (2013). Case study 1 : The Delhi Airport Metro Express project. PPIAF. Retrieved from https://library.pppknowledgelab.org/documents/5271?ref_site=ppiaf&restrict_documents=false&restrict_pages=true§or%5B%5D=light%20rail%20and%20metro&site_source%5B%5D=PPIAF
- Baker, J., & Nixon, S. (2006, March, 11). For sale: Ghost train to Sydney Airport. The Sydney Morning Herald. Retrieved from https://www.smh.com.au/national/for-sale-ghost-train-to-sydney-airport-20060311-gdn4qj.html
- Balachandran, M. (2013, December, 5). India's PPP dream for roads turns sour. Business Standard. Retrieved from https://www.business-standard.com/article/economy-policy/india-s-ppp-dream-for-roads-turns-sour-113120500029_1.html
- Bhatt, A. (2019, September, 15). High cost, low ridership, location ensured failure of Gurgaon Rapid Metro. The Hindustan Times. Retrieved from https://www.hindustantimes.com/opinion/expensive-mistakes-high-cost-low-ridership-location-ensured-failure-of-the-rapid-metro-opinion/story-KEIXsoxNDQztk5Mu6HHBDN.html
- Bhowmick, S., & Basu, P. (2019, November, 23). Is India’s Vizhinjam Port Plan worth it ? The Diplomat. Retrieved from https://thediplomat.com/2019/11/is-indias-vizhinjam-port-plan-worth-
- Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006
- Carbonara, N., Costantino, N., Gunnigan, L., & Pellegrino, R. (2015). Risk management in motorway PPP projects: Empirical-based guidelines. Transport Reviews, 35(2), 162–182. http://dx.doi.org/10.1080/01441647.2015.1012696
- Casady, C. B. (2020). Examining the institutional drivers of public-private partnership (PPP) market performance : A fuzzy set qualitative comparative analysis (fsQCA). Public Management Review, 1-25. https://dx.doi.org/10.1080/14719037.2019.1708439
- Chao, J. J., & Harris, C. G. (2016). Public private infrastructure advisory facility (PPIAF) annual update report 2016 (English). Public-Private Infrastructure Advisory Facility (PPIAF). Washington, DC.: World Bank. Retrieved from http://documents.worldbank.org/curated/en/685801507287970140/Public-Private-Infrastructure-Advisory-Facility-PPIAF-annual-upate-report-2016
- Compliance Advisor Ombudsman. (2018). CAO assessment report. Washington DC : Office of the Compliance Advisor Ombudsman.
- Cross City tunnel sold to Transurban for $475m. (2014, March, 27). The Sydney Morning Herald. Retrieved from https://www.smh.com.au/business/cross-city-tunnel-sold-to-transurban-for-475m-20140327-35klq.html
- Darvish, H., Zou, P. X., Loosemore, M., & Zhang, G. M. K. (2006). Risk management, public interests and value for money in PPP projects: Literature review and case studies. In, Proceedings of CRIOCM 2006 International Research Symposium on Advancement of Construction Management and Real Estate (pp. 546 –557). Beijing : Chinese Research Institute of Construction Management.
- DeGood, K. (2019, December, 11). The limits of risk transference through public-private partnerships. Center for American Progress. Retrieved from https://www.americanprogress.org/issues/economy/reports/2019/12/11/478265/limits-risk-transference-public-private-partnerships/
- Duke, A. (2020, April, 9). FDOT to pay I-4 ultimate contractors an additional $125 million to finish project. Wesh2. Retrieved from https://www.wesh.com/article/fdot-to-pay-i-4-ultimate-contractors-an-additional-dollar125-million-to-finish-project/32098965
- EIU. (2019, September, 6). Infrastructure reform mitigates energy sector dysfunction. The Economics Intelligence Unit. Retrieved from http://country.eiu.com/article.aspx?articleid=1968370980&Country=Ghana&topic=Politics&subtopic=Na_1
- Ghana pays $28 million, not $40 million for take-or-pay gas contract-Energy ministry. (2019, January, 3). Ghana Web. Retrieved from https://www.ghanaweb.com/GhanaHomePage/business/Ghana-pays-28-million-not-40-million-for-Take-or-Pay-gas-contract-Energy-Ministry-712536
- Global Infrastructure Hub. (2018). Port of Miami Tunnel. Retrieved from https://content.gihub.org/live/media/1440/
- Gurugram Rapid Metro is in trouble, here's why nobody wants to run it. (2019, September, 14) LiveMint. Retrieved from https://www.livemint.com/news/india/gurgaon-rapid-metro-is-in-trouble-here-s-why-nobody-wants-to-run-it-1568436349198.html
- Hammami, M., Ruhashyankiko, J. - F., & Yehoue E. B. (2006). Determinants of public-private partnerships in infrastructure (IMF Working Paper WP/06/99). Retrieved from https://www.imf.org/external/pubs/ft/wp/2006/wp0699.pdf
- Hazen, B. (2020, February, 24). $150K public art installation approved for Winter Park thanks to I-4 Ultimate Project. Wesh2. Retrieved from https://www.wesh.com/article/dollar150k-public-art-installation-approved-for-winter-park-thanks-to-i-4-ultimate-project/31085357
- Irigoyen, C. (2017, July, 28). The Bujagali Dam project in Uganda. Centre for Public Impact. Retrieved from https://www.centreforpublicimpact.org/case-study/bujagali-dam-project-uganda/
- Kumar, S. S. (2017, November 28). How the Telangana govt made the Hyderabad Metro Rail possible. Telangana Today. Retrieved from https://telanganatoday.com/how-telangana-govt-made-hyderabad-metro-rail-possible
- Larsen & Toubro. (2015). 70th annual report 2014–2015. Delhi : L&T.
- Marotta, M. (2011). Management and financial analysis report of the Taiwan High Speed Railway project. https://dx.doi.org/10.13140/RG.2.2.26574.97600
- Maslyukivska, O., & Sohail, M. (2007). European infrastructure procurement through PPP. Proceedings of the Institution of Civil Engineers - Management, Procurement and Law, 160(4), 159-167. https://dx.doi.org/10.1680/mpal.2007.160.4.159
- Ministry of Finance. (2018). Delhi-Gurgaon Expressway. New Delhi : Ministry of Finance, Government of India.
- Newman, J. (2017). Governing public-private partnerships. Canada: McGill-Queen's Press-MQUP.
- Ni, J., Chang, J., & Kao, T. C. (2016). 8 Taiwan’s HSR and the financial crises of the Taiwan High Speed Rail Corporation. In, B. L. Pérez Henríquez & E. Deakin (eds.). High-speed rail and sustainability : Decision-making and the political economy of investment (pp. 119-126). London : Routledge.
- PFAL. (2016). I-4 ultimate P3. San Fransciso: Project Finance Advisory Ltd. Retrieved from https://scta.ca.gov/wp-content/uploads/2016/12/PFAL_I-4_CaseStudy-FINAL.pdf
- Pilling, D. (2018, March, 17). World Bank set for Uganda dam refinancing talks despite criticism. Financial Times. Retrieved from https://www.ft.com/content/9218ca3e-214b-11e8-a895-1ba1f72c2c11
- Private Participation in Infrastructure Database. (2019). Private participation in infrastructure (PPI) database. Washington, DC: World Bank.
- Prasad, N. (2019, October, 24). Delhi Metro takes over operations of Rapid Metro Gurgaon ! Financial Express. Retrieved from https://www.financialexpress.com/infrastructure/delhi-metro-takes-over-operations-of-rapid-metro-gurgaon-check-details-of-stations-timings-here/1743703/
- Projects Monitor. (2014, April, 18). L&T to exit from two road projects in Maharashtra. Projects Today. Retrieved from https://www.projectsmonitor.com/daily-wire/lt-to-exit-from-two-road-projects-in-maharashtra/
- Radhakrishnan, S.A. (2016, March 29). Vizhinjam to become reality. The Hindu. Retrieved from https://www.thehindu.com/news/national/kerala/kerala-all-set-to-sign-pact-with-adani-vizhinjam-ports-ltd/article7547107.ece
- Rajasekar, T., & Aravanan, S. (2011). Financial performance analysis of major ports in India - A study with special reference to Tuticorin Port Trust. Indian Journal of Finance, 5(9), 45-57.
- Ray, S. (2017, May, 12). Delhi Airport Metro : DMRC told to pay ReIiance Infra Rs 2,950cr after 3-year arbitration. The Hindustan Times. Retrieved from https://www.hindustantimes.com/delhi-news/rinfra-wins-rs2-950-cr-arbitration-award-against-dmrc-over-airport-metro/story-dkCLVaRvecPFmuzYO6EiCI.html
- Saulon, V.V. (2019, October, 23). Ghana gov’t terminates concession for ECG. Business World. Retrieved from https://www.bworldonline.com/ghana-govt-terminates-concession-for-ecg/
- Seetharaman, G. (2018, September, 01). Five years on, has land acquisition act fulfilled its aim? The Economic Times. Retrieved from https://economictimes.indiatimes.com/news/economy/policy/five-years-on-has-land-acquisition-act-fulfilled-its-aim/articleshow/65639336.cms?utm_source=contentofinterest&utm_medium=text&utm_campaign=cppst
- Sharma, S., & Sharma, S.K. (2017). Development of ITC E- choupal based rural financial inclusion model. Indian Journal of Finance, 11(10), 20–32. https://dx.doi.org/10.17010/ijf/2017/v11i10/118773
- Solomon, P., & Aggarwal, T. (2020). Technology entrepreneurship in real estate sector development in India : PPP model. Indian Journal of Finance, 14(3), 22–35. https://dx.doi.org/10.17010/ijf/2020/v14i3/151075
- Song, J., Hu, Y., & Feng, Z. (2018). Factors influencing early termination of PPP projects in China. Journal of Management in Engineering, 34(1), 05017008. https://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000572
- Spear, K. (2019, October, 25). I-4 ultimate : Delays, overruns and deaths plague project. Orlando Sentinel. Retrieved from https://www.orlandosentinel.com/news/transportation/os-ne-interstate-4-construction-trouble-20191024-bwu7si7rwzbz7kebzurpoazuhu-story.html
- Tiwari, S. (2015, October, 19). Hardlook: Dwarka Expressway’s seven-year hitch. The Indian Express. Retrieved from https://indianexpress.com/article/cities/delhi/hardlook-dwarka-expressways-seven-year-hitch/
- Tripathi, S. (2015). Syndication of VCPE investments: Evidence from the Indian infrastructure sector. Indian Journal of Finance, 9(7), 32–42. https://dx.doi.org/10.17010/ijf/2015/v9i7/72352
- Wibowo, A., & Alfen, H. W. (2015). Government-led critical success factors in PPP infrastructure development. Built Environment Project and Asset Management, 5(1), 121-134. https://dx.doi.org/10.1108/BEPAM-03-2014-0016
- World Bank Institute. (2017). PPP reference guide-Version 3. Washington, DC: World Bank.
- World Bank. (2016). The state of PPPs: Infrastructure public-private partnerships in emerging markets and developing economies 1991-2015. Washington, DC : The World Bank and PPIAF.
- World Bank. (2018). Implementation completion and results report. Washington, DC: World Bank.
- Yin, R. K. (2014). Case study research design and methods (5th ed.). Thousand Oaks, CA: Sage.
- Yu, Y., Chan, A. P., Chen, C., & Darko, A. (2018). Critical risk factors of transnational public-private partnership projects : Literature review. Journal of Infrastructure Systems, 24(1), 04017042. https://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000405
- Zhang, L., Sun, X., & Xue, H. (2019). Identifying critical risks in Sponge City PPP projects using DEMATEL method : A case study of China. Journal of Cleaner Production, 226, 949–958. https://dx.doi.org/10.1016/j.jclepro.2019.04.067
Abstract Views: 290
PDF Views: 0