Case Study : Distortion Control in Orthotropic Steel Deck Welding


Affiliations
1 Larsen & Toubro Limited (L&T Construction), MTHL PKG-1, STP Yard Gate No. 1, Near Sewri Railway Station, Sewri (East), Mumbai- 400015, India
     

   Subscribe/Renew Journal


Orthotropic Steel Deck (OSD) Bridge is typically a long span bridge around the world. The OSD bridge construction has numerous advantages. OSD has a complete steel superstructure, offering high stiffness to weight ratio, reduces the dead load on foundation of bridge and enables to provide longer span of bridge. This case study particularly deals with achieving bridge camber value during assembly and erection of Orthotropic Steel Deck by adopting suitable methodologies & techniques. The main challenges encountered during implementation of OSD bridge were (a) selecting suitable welding process/techniques, (b) shrinkage control during assembly and erection, (c) thermal expansion during weld joint fit up in marine environment. This case study may be useful for the construction industries adopting Orthotropic Steel Deck technology to construct long span bridges. One of typical span is sampled here to explain the above challenges and methods adopted to overcome them.

Keywords

Orthotropic Steel Deck, Thermal Expansion, Welding Shrinkage, Design Camber.
User
Subscription Login to verify subscription
Notifications
Font Size

Abstract Views: 258

PDF Views: 3




  • Case Study : Distortion Control in Orthotropic Steel Deck Welding

Abstract Views: 258  |  PDF Views: 3

Authors

P. Raja Rethinam
Larsen & Toubro Limited (L&T Construction), MTHL PKG-1, STP Yard Gate No. 1, Near Sewri Railway Station, Sewri (East), Mumbai- 400015, India
S. Sampath Kumar
Larsen & Toubro Limited (L&T Construction), MTHL PKG-1, STP Yard Gate No. 1, Near Sewri Railway Station, Sewri (East), Mumbai- 400015, India
Thomas Alphones
Larsen & Toubro Limited (L&T Construction), MTHL PKG-1, STP Yard Gate No. 1, Near Sewri Railway Station, Sewri (East), Mumbai- 400015, India

Abstract


Orthotropic Steel Deck (OSD) Bridge is typically a long span bridge around the world. The OSD bridge construction has numerous advantages. OSD has a complete steel superstructure, offering high stiffness to weight ratio, reduces the dead load on foundation of bridge and enables to provide longer span of bridge. This case study particularly deals with achieving bridge camber value during assembly and erection of Orthotropic Steel Deck by adopting suitable methodologies & techniques. The main challenges encountered during implementation of OSD bridge were (a) selecting suitable welding process/techniques, (b) shrinkage control during assembly and erection, (c) thermal expansion during weld joint fit up in marine environment. This case study may be useful for the construction industries adopting Orthotropic Steel Deck technology to construct long span bridges. One of typical span is sampled here to explain the above challenges and methods adopted to overcome them.

Keywords


Orthotropic Steel Deck, Thermal Expansion, Welding Shrinkage, Design Camber.



DOI: https://doi.org/10.22486/iwj.v55i3.213076